Northern Spire Bridge in Sunderland Opens To Traffic

30th August 2018

Sunderland’s stunning new Northern Spire bridge has opened to traffic this week, following three years of construction on the Sunderland site.

The landmark bridge across the River Wear, with its majestic 105m central A-frame pylon, was opened at 11.10am on Wednesday 29th August, with the first members of the public driving, riding and walking across seconds later.

 

Northern Spire is the result of an innovative three-year construction programme that saw 2,000 people work more than a million hours to build the impressive crossing, which is now the tallest structure in North East England.

On Tuesday, members of the public were given an opportunity to walk across the bridge before it opened, with thousands of people turning out to stroll across the 340m deck.

The bridge was then officially opened to traffic following a short unveiling ceremony, which saw Sunderland City Council Leader Cllr Graeme Miller and Project Director Stephen McCaffrey, who led the construction for Farrans Victor Buyck (FVB) Joint Venture, make speeches before a red ribbon was cut.

 

Catalyst for Regeneration 

“It is a great honour to be here today to open this landmark bridge,” said Cllr Miller.

 

“Northern Spire isn’t just an asset for our city, but one for the wider region as a whole. In Sunderland, it will act as a catalyst for regeneration and investment on both banks of the River Wear and will help to create over 6,000 jobs in a city that is signalling its ambition with investment and making it absolutely clear that we’re open for business.

 

“Of course, the benefits go beyond the economic ones and this stunning structure will not only allow our communities to move around the city more easily, but it will instil a sense of confidence and pride for our residents in the place they call home.

 

“All of this said, it is no wonder that the council fought so hard over many years to make this happen and to ensure that Northern Spire exists in its current, impressive form. It’s taken three years to build, but many more years in gaining support locally, regionally and nationally, and we should all feel incredibly proud of what has been achieved.”

 

After the ribbon was cut, Cllr Miller, Stephen McCaffrey, Mayor of Sunderland Cllr Lynda Scanlan and Sunderland City Council Chief Executive Patrick Melia were escorted to three waiting Sunderland-built Nissan vehicles, including the record breaking Qashqai and 100% electric LEAF, which were the first vehicles to officially drive across the completed bridge.

 

 

A beautiful structure with many challenges and complexities

 

Stephen said: “It is with immense pride and satisfaction that I’m here at the opening of Northern Spire.

 

“It has been an incredible construction project to be involved in with so many challenges and complexities, and I think I can speak for the whole team when I say that it’s something we will all remember for the rest of our careers. Projects like this, with all of its unique methodologies and milestones, such as the raising of the central pylon and the launching of the bridge deck across the river, don’t come along very often.

 

“Of course, it could not have been achieved without the ambition and foresight of Sunderland City Council, whose determination and hard work to make it a reality began decades ago.

 

“As Project Director, however, I would also like to pay tribute to everyone who has worked on this project. We have had an amazing team of people, both from the local area and wider North East, as well as from overseas, and it is their talent, skill and experience that has brought this bridge to life. Everyone should feel proud of their efforts.

 

“Northern Spire is a beautiful structure. I hope the people of Sunderland take it to their hearts as much as the team on site has.” 

 

 

Part of the Sunderland Strategic Transport Corridor

 

Work began on Northern Spire in May 2015. It links Pallion, south of the river, with Castletown, to the north, and is the first bridge to be built across the Wear in more than 40 years. It will open up land for regeneration, reduce congestion and journey times around the city, and help to boost the economy.

 

It has been built within its £117m budget and is part of a wider five-phase plan, the Sunderland Strategic Transport Corridor (SSTC) by Sunderland City Council to improve the road network between the A19 and Sunderland city centre and Port of Sunderland. The next phase, a dual carriageway between Northern Spire and the city centre, is expected to be complete in 2021.